Free template · Quality and snags

A room-wise snag list template for interior projects

A snag list template records every defect found before handover: the room, item, description, photo, who fixes it, the target date and its status. It is also called a punch list. Walk the site room by room with the client, log each snag, and close every line before you ask for the handover payment. The quality checklists below help you find snags before the client does.

On this page

  1. The snag list template
  2. When to run a snag walk
  3. Field-by-field explanation
  4. Quality checklists by trade
  5. Common mistakes
  6. Making it in Google Sheets
  7. Snag lists in the D&B Operating System

The snag list template

#RoomItemSnag descriptionPhotoTrade / ownerTarget dateStatus
1Master bedroomWardrobeRight shutter gap uneven at topP-14Carpentry22 OctOpen
2LivingFalse ceilingHairline crack at board joint near coveP-15Ceiling23 OctOpen
3KitchenCountertopSilicone missing behind sinkP-16Kitchen installer21 OctClosed
4Bedroom 2PaintPatchy finish near switchboardP-17Painting24 OctOpen
5BathroomTilesOne hollow-sounding tile near drainP-18Tiling24 OctOpen

Sample snags for illustration.

When to run a snag walk

Run an internal snag walk first, with your project manager and supervisor, about a week before planned handover. Fix what you find. Then run the client snag walk, with the client present, and log what they point out.

Close the list, re-walk with the client, and only then sign the handover. A punch list template works the same way on commercial fit-outs, where the client's facility team usually leads the walk.

Field-by-field explanation

Quality checklists by trade

TradeWhat to check
Tile layingLevel and slope to drains, even joints, no hollow sound on tapping, clean grout, cut tiles at less visible edges
Paint finishEven colour under daylight and lamps, no patches, brush marks or drips, clean edges at ceiling and switchboards
False ceilingLevel across the room, no cracks at joints, cove lines straight, cut-outs aligned, access panels where needed
WoodworkShutters aligned with even gaps, soft-close working, edge banding sealed, no chips or swelling
ElectricalEvery point works, switches labelled, lights aligned, no loose plates
PlumbingNo leaks under sinks, taps tight, drains clear, sealant complete

Common mistakes

Making it in Google Sheets

  1. Create the columns above, with a drop-down for status and one for trade.
  2. Insert photos with Insert, Image in cell, or paste a photo link.
  3. Filter by trade and share each trade's list with its team.
  4. Add a count of open snags at the top using COUNTIF on the status column.

Snag lists in the D&B Operating System

The D&B Operating System includes a snag list for project managers before handover. The handover stage in its workflow covers snags closed, final invoice raised and payment received, so the last payment follows the closed list. It is software by BRANDSWOT Consultancy, now in early access.

Questions people ask

What is a snag list template for interiors?

It is a table of defects found before handover, with room, item, description, photo, the trade responsible, target date and status. You walk the site room by room, log each snag, fix it and re-check with the client. Closing it is usually the condition for the handover payment.

What should a snag list format for interior work include?

Include a snag number, room, item, a short description of the defect, a numbered photo, the owner, target date and status. Add a column for client re-check. Keep one list per project and report the open count daily in the last week. Share it with each trade daily.

What is a punch list template?

A punch list is the same as a snag list: a list of incomplete or defective items to fix before final acceptance. The term is common on commercial fit-outs. Use the same columns: location, item, issue, photo, owner, due date and status. Get final sign-off when all items close.

What goes on a quality checklist for interior works?

Check each trade against clear points: tiles level and not hollow, paint even under daylight, ceiling level with straight coves, woodwork aligned with even gaps, every electrical point working, and no plumbing leaks. Run it before the client walk so most snags are found internally.

What is on a tile laying checklist?

Check the surface is level, wet areas slope towards drains, joints are even and straight, there is no hollow sound on tapping, grout is complete and clean, and cut tiles sit at less visible edges. Check before the grout cures fully so fixes are easier.

What should a paint finish checklist and false ceiling checklist cover?